St Mary's Harbour Improvement Project Weekly Update Week …

Here s the update on the Quay works from Kier

Quay Extension:

12th Slab poured 2 remain. Fenders 13 of 19 installed. Remainder on-going. Quay Widening:

First 4 Slab pours complete.

Backfilling around tanks on-going. Drainage installation on-going. Further slab pours to follow. Wall construction commenced.

Harbourside building

Freight Offices New DB installed works to install chiller works & electrical feed ongoing. Freight Store 2nd fix electrics this week

Balcony Balustrades Cladding & decking complete. Chiller Testing and commissioning this week.

ACO channel installation complete. Sliding doors fitted, testing ongoing, guttering to follow. Parting Carn:

Batching concrete for quay extension and widening foundations continues.

Demobilisation ongoing. Stone cutting for new wall installation to quay widening. Porthloo:

Recycling of the dredged material at Porthloo continues using Tractor Trailer and a Wheeled Excavator.

All large boulders will be retained and used in the sea defences.

Kier has installed cameras on all working vehicles with a recording facility for appraisals and record purposes.